[upstream] Update the Release cycle section
Update the content, add new exercise and remove the outdated diagram. Change-Id: I6152e45570be93ae84a99370ee60d2b9ff9129ed
This commit is contained in:
parent
8c35dc58c6
commit
4e2845d1d1
Binary file not shown.
Before Width: | Height: | Size: 27 KiB |
@ -10,159 +10,172 @@ What makes a release
|
||||
====================
|
||||
|
||||
- A way to coordinate the development of multiple projects
|
||||
- Until Kilo "integrated release" meant a date when all the projects
|
||||
are released at the end of the development cycles
|
||||
- Integrated projects were also tested together at the gate
|
||||
- For Liberty integrated projects are those managed by the Release
|
||||
Management Team
|
||||
- Other projects may have different schedules
|
||||
- Release process is managed by the Release Management team
|
||||
- Release models
|
||||
|
||||
- Each project team page shows its release policy on
|
||||
http://governance.openstack.org/reference/projects
|
||||
- *Common cycle with development milestones*
|
||||
- Common cycle with intermediary release
|
||||
- Trailing the common cycle
|
||||
- Independent release model
|
||||
|
||||
Planning : Design
|
||||
.. note::
|
||||
|
||||
- Release management description:
|
||||
http://docs.openstack.org/project-team-guide/release-management.html
|
||||
- The training concentrates on the common cycle with the development
|
||||
milestones as that is what most students will face with. The other types
|
||||
should be described with examples.
|
||||
|
||||
Exercise
|
||||
========
|
||||
|
||||
- Look up the release schedule for the current and past two OpenStack
|
||||
release cycles
|
||||
- Identify common caracteristics of these cycles
|
||||
|
||||
- Milestones
|
||||
- Deadlines
|
||||
- etc.
|
||||
|
||||
- Describe a release cycle based on the information you found
|
||||
|
||||
Common cycle with development milestones
|
||||
========================================
|
||||
|
||||
- A coordinated way for projects to periodically create their deliverables
|
||||
including testing and documentation
|
||||
- Every cycle includes
|
||||
|
||||
- Planning and design activities
|
||||
- Implementation work
|
||||
|
||||
- New features
|
||||
- Bug fixes
|
||||
- Testing
|
||||
- Documentation
|
||||
|
||||
- Release preparation
|
||||
- Release
|
||||
|
||||
Planning - Design
|
||||
=================
|
||||
|
||||
.. rst-class:: colleft
|
||||
- Design activity is a continuous effort
|
||||
- Planning for a release cycle starts at the end of the previous cycle
|
||||
- It depends on each project how to organise the work at each cycle
|
||||
|
||||
- Planning stage is at the start of a cycle
|
||||
- Take a step back
|
||||
- Focus on what we want to do for the next one
|
||||
- Spec/blueprint freeze
|
||||
- Prioritising items
|
||||
|
||||
.. rst-class:: colright
|
||||
- Generic intention behind planning
|
||||
|
||||
.. image:: ./_assets/01-01-release.png
|
||||
- Take a step back
|
||||
- Focus on what we want to do for the next one
|
||||
|
||||
Planning : Discuss
|
||||
Planning - Discuss
|
||||
==================
|
||||
|
||||
.. rst-class:: colleft
|
||||
- Prepare your idea for the public
|
||||
|
||||
- With our peers
|
||||
- Feedback and comments
|
||||
- Create the corresponding blueprint
|
||||
- 4 weeks, Design Summit on the third week
|
||||
- Discuss with your peers
|
||||
- Work on feedback and comments
|
||||
|
||||
.. rst-class:: colright
|
||||
- Capture your idea in a spec/blueprint
|
||||
|
||||
.. image:: ./_assets/01-01-release.png
|
||||
|
||||
Planning : Target
|
||||
Planning - Target
|
||||
=================
|
||||
|
||||
.. rst-class:: colleft
|
||||
- Submit the blueprints and/or specs
|
||||
- Identify a target milestone
|
||||
|
||||
- File new blueprints and/or specs
|
||||
- Set a target milestone
|
||||
- When in the cycle they intend to complete it
|
||||
- PTLs triage the submitted blueprints and set priority
|
||||
|
||||
.. rst-class:: colright
|
||||
|
||||
.. image:: ./_assets/01-01-release.png
|
||||
|
||||
Implementation : Milestone
|
||||
==========================
|
||||
|
||||
.. rst-class:: colleft
|
||||
|
||||
- Pushed to Gerrit for peer review
|
||||
- Weeks before the milestone publication date
|
||||
- Milestone-proposed branch
|
||||
- Feature-frozen
|
||||
|
||||
.. rst-class:: colright
|
||||
|
||||
.. image:: ./_assets/01-01-release.png
|
||||
|
||||
Implementation : freezes
|
||||
========================
|
||||
|
||||
.. rst-class:: colleft
|
||||
- When in the cycle you intend to complete it
|
||||
- Project team helps you to identify the target milestone and register it
|
||||
in the tracking tool
|
||||
|
||||
- The priority of the work item is set by the project team members or lead
|
||||
- Feature proposal freeze
|
||||
|
||||
- Not even proposals for features will be accepted
|
||||
- Focus on bug-fixing
|
||||
- The deadline for proposing new ideas for a release cycle
|
||||
- The exact date depends on the projects
|
||||
|
||||
Exercise
|
||||
========
|
||||
|
||||
- Find feature proposal deadlines in the current release schedule
|
||||
|
||||
Implementation
|
||||
==============
|
||||
|
||||
- When your blueprint/spec is accepted
|
||||
|
||||
- Push code to Gerrit for review
|
||||
- Upload your code as early as possible in the release cycle
|
||||
|
||||
- Deadlines for the code to get merged
|
||||
|
||||
- Depends on the priority of your work item
|
||||
- Set by each project team
|
||||
|
||||
Implementation - Milestone
|
||||
==========================
|
||||
|
||||
- Three development milestones during a release cycle
|
||||
- Make useful reference points in time to organize the development cycle
|
||||
- Milestones are tagged in the repository using b1, b2 and b3
|
||||
- Overall feature freeze is the third milestone
|
||||
|
||||
Implementation - Freezes
|
||||
========================
|
||||
|
||||
- Freeze dates depend on the type of activity
|
||||
- Feature freeze
|
||||
|
||||
- New features will not be accepted, only fixes
|
||||
- Code for new features will not be accepted
|
||||
- Bug fixing activities are still ongoing
|
||||
- More focus on testing
|
||||
|
||||
- String freeze
|
||||
|
||||
- All externally visible strings must be frozen
|
||||
- This helps the i18n and Documentation projects
|
||||
|
||||
.. rst-class:: colright
|
||||
|
||||
.. image:: ./_assets/01-01-release.png
|
||||
- This helps the I18n and Documentation projects
|
||||
|
||||
Release Candidates
|
||||
==================
|
||||
|
||||
.. rst-class:: colleft
|
||||
|
||||
- After the last milestone
|
||||
- Code stabilization period
|
||||
- Main activities
|
||||
|
||||
- File bugs about everything you find
|
||||
- Test the code and file bugs
|
||||
- Prioritize bugs / bug triage
|
||||
- Write documentation
|
||||
- Fix as many bugs as you can
|
||||
|
||||
.. rst-class:: colright
|
||||
- Get critical and high priority bugs fixed on the first place
|
||||
- Fix as many bugs as possible
|
||||
|
||||
.. image:: ./_assets/01-01-release.png
|
||||
- Finalize documentation
|
||||
|
||||
Release candidate 1
|
||||
===================
|
||||
|
||||
.. rst-class:: colleft
|
||||
|
||||
- Between the last milestone and the RC1
|
||||
|
||||
- Stop adding features and concentrate on bug fixes
|
||||
- Once all the release-critical bugs are fixed, we produce the first release
|
||||
candidate for that project (RC1)
|
||||
- Used as-is as the final release
|
||||
|
||||
|
||||
.. rst-class:: colright
|
||||
|
||||
.. image:: ./_assets/01-01-release.png
|
||||
- Cut when all the release-critical bugs are fixed
|
||||
- stable/release branch
|
||||
- master branch is open for development
|
||||
- Used as-is as the final release
|
||||
|
||||
Other release candidates
|
||||
========================
|
||||
|
||||
.. rst-class:: colleft
|
||||
|
||||
- Regressions and integration issues
|
||||
|
||||
- New release-critical bugs
|
||||
|
||||
- (RC2), with bugs targeted to it
|
||||
- (RC2, RC3, ...), with bugs targeted to it
|
||||
|
||||
- Merged in the master branch first
|
||||
- Merged in the master branch first and then cherry-picked to stable
|
||||
- Repeated as many times as necessary
|
||||
|
||||
.. rst-class:: colright
|
||||
|
||||
.. image:: ./_assets/01-01-release.png
|
||||
|
||||
Release day
|
||||
===========
|
||||
|
||||
.. rst-class:: colleft
|
||||
|
||||
- Last published release candidate
|
||||
- Published collectively as the OpenStack release
|
||||
|
||||
.. rst-class:: colright
|
||||
|
||||
.. image:: ./_assets/01-01-release.png
|
||||
|
||||
Exercise
|
||||
========
|
||||
|
||||
Based on the Kilo release schedule, find the URL of a document or a patch
|
||||
that belongs to each of the steps.
|
||||
|
Loading…
x